Estado:
Complete
Location:
Naxos - Greece
Region:
Europe
Total cost:
USD $0
Duration:
2 years
Start:
02 May 2011
End:
06 May 2013
Working Areas
Asset Management
Energy Efficiency and Climate Change Mitigation
Non-Revenue Water (NRW 1): Commercial Losses Management
Operation & Maintenance
Organizations Involved
Municipality of Naxos and Lesser Cyclades — Lead Mentee
  • Municipality of Amorgos — Mentee
Athens Water Supply and Sewerage Company — Lead Mentor
WOP SEE
Broker
Geosfaira S.A. Expertise in landscape GIS models
Techical Support
TEC S.A.
Techical Support
SDGs
6.4Increased water-use efficiency and sustainable withdrawals and supply of freshwater
Project description
This is series 3 of 3, for the 9 operators which aims to maximize existing infrastructur
Project main objectives
Utilization of existing infrastructure, dimensioning of investments according to actual requirements, optimal management of scarce water resources.