Estado:
Complete
Location:
Da Nang - Vietnam
Region:
Asia
Total cost:
USD $2,700,000
Duration:
3 years 2 months
Start:
18 October 2007
End:
30 December 2010
Working Areas
Asset Management
Catchment Management/ Integrated Water Resource Management – IWRM
Customer Relations
Financial Management
Non-Revenue Water (NRW 1): Commercial Losses Management
Operation & Maintenance
Service in Low-Income Areas
Tariff Setting
Other
Organizations Involved
Da Nang Water Supply Company — Lead Mentee
VEI Dutch Water Operators — Lead Mentor
DGIS - Directorate - General for International Cooperation Netherlands
Funder
Ministry of Foreign Affairs of the Netherlands
Funder
Dutch Embassy in Vietnam
Funder
SDGs
6.1Universal and equitable access to safe and affordable drinking water for all
Project description
The VEI-Dawaco WOP was carried out from 2007 until the end of 2010. The WOP focused on the extension and improvement of water services in Da Nang, while supporting Dawaco in achieving management autonomy and a stronger financial position. Besides the achieved operational, managerial, and financial water utility performance improvements, the WOP was successful in supporting water services for the urban poor. Through improved processes and pro-poor strategies, the WOP’s approach allowed for Dawaco to build on its own capacity and contribute to the sustainability of results, including effective, long-term and inclusive water delivery.
Project main objectives
1. the extension and improvement of water services in Da Nang,
2. the management autonomy and strengthening of Dawaco’s financial position, and
3. the sustainable delivery of water services to the urban poor.
Most significant results
• Non-Revenue Water has gone down during the years since the start of the WOP from approximately 39% to 26% at the end of the partnership, and 15% by 2017.
• Nearly 49,000 new connections were made, averaging over 16,000 per year.
• Over 7,800 connections for the poor were made, averaging around 2,600 per year and amounting to 16% of the total new connections.
• Water quantity and quality meters were installed at two water treatment plants. With this, 99% of total production was metered. Based on the data collected from these meters the operational processes were improved.
• A Central Control Unit was officially implemented and metering equipment was installed in the network.
• A new tariff structure was approved which made low consumption costs accessible to the poor who generally use a limited amount of water.
• Sustained progress of performance improvements even after the WOP ended, as shown with the increased connectivity rates, current NRW values, and improved creditworthiness of the company evaluated from 1996 to 2017.
• Operational, managerial, and financial water utility performance improvements paved the road for access to other funding opportunities (ADB, JICA, and the World Bank) which further supported the objectives of the WOP.